I3841 — The plan's graph is drawn by milestone, so /plan/dag/ answers the site probe within its budget however large the backlog grows

Bound what /plan/dag/ and /plan/ draw by the number of milestones rather than the number of issues: scripts/generate-site-data adds to plan.json a milestone graph (milestone_edges, one entry per pair of milestones an issue dependency crosses, counted, and milestone_mermaid, one node per milestone with its done count and status), both pages draw it, /plan/dag/ lists the milestone edges as its text equivalent and points to the waves on /plan/, and every milestone node links to the milestone's own page, which already draws its issues; a case holds /plan/dag/ to an element ceiling and its graph to one node per milestone.

READY wave 0 · p1 · implementation profile · parallel safe

Part of a-change-is-judged-in-minutes — A change is derived in under a second and judged in minutes, and nothing that could have changed is skipped.

Ready. Every dependency is done, so majordomus plan start I3841 will be accepted.

Objective

Bound what /plan/dag/ and /plan/ draw by the number of milestones rather than the number of issues: scripts/generate-site-data adds to plan.json a milestone graph (milestone_edges, one entry per pair of milestones an issue dependency crosses, counted, and milestone_mermaid, one node per milestone with its done count and status), both pages draw it, /plan/dag/ lists the milestone edges as its text equivalent and points to the waves on /plan/, and every milestone node links to the milestone's own page, which already draws its issues; a case holds /plan/dag/ to an element ceiling and its graph to one node per milestone.

Why

On 2026-10-21 master's validate 39645593645 (97391192dbb, the 1.0.0-alpha.4 head) went red in site-probe-shard (5): /plan/dag/ did not answer within 90 s. Measured that day (6a2e) on majordomus.dev with headless Chrome at 1536 px: 26,881 elements, 1,202,261 bytes, 44,748 px tall, a mermaid graph of every issue (824 nodes, 779 edges, 82,663 characters of source), an edge table of 779 rows that looks every issue up twice per row, and the waves listing all 801 issues again (the same lists /plan/ carries). Every one of those grows with the backlog; the graph's layout grows faster than linearly in it. This is the remainder I3838 named (the plan graph about 12,700 of the 21,589 elements /plan/ had left). The milestone graph is 100 nodes, 111 counted edges and 18,600 characters at the same tree, and each milestone's page already draws its own issues (at most 11,008 characters). Id I3841 and case 3860 from 9c (board id-I3841-6a2e); a3 asked for it for train 4.

Current state

/plan/dag/ and /plan/ draw plan.mermaid, the graph of every issue; /plan/dag/ also prints every issue edge and every wave in full.

Desired state

/plan/dag/ and /plan/ draw plan.json's milestone_mermaid, one node per milestone with counted arrows; /plan/dag/ prints the milestone edges with the issue pairs behind each and links to the waves on /plan/; scripts/site-check holds every edge of plan.json to the page that owns it (a milestone edge to the graph /plan/dag/ draws, an edge inside a milestone to that milestone's graph, an edge that crosses milestones to the list on /plan/dag/); every issue edge stays in plan.json's edges and in majordomus plan graph, and each milestone's page draws its issues; a case fails when /plan/dag/ passes its element ceiling or its graph stops being one node per milestone.

Scope

  • site/templates/dag.html
  • site/templates/plan-section.html
  • scripts/generate-site-data
  • scripts/site-check
  • test/cases/3860_the_plan_graph_is_drawn_by_milestone.sh
  • site/content
  • site/data/generated
  • docs/generated

Out of scope

  • Raising the site probe's 90 s budget or excluding /plan/dag/ from it
  • The milestone pages' own graphs, which draw one milestone's issues
  • How majordomus plan graph draws the whole graph at a terminal

Dependencies

None. This issue is a root of the graph.

Acceptance criteria

  • plan.json carries milestone_edges and milestone_mermaid; the graph has one node per milestone and one counted arrow per pair of milestones an issue dependency crosses, and the counts add up to the cross-milestone issue edges
  • /plan/dag/ and /plan/ draw the milestone graph and not the graph of every issue; every milestone node links to the milestone's page
  • A case fails when /plan/dag/ in the built site passes its element ceiling, and passes at the tree it lands with
  • The site probe visits /plan/dag/ within its budget

Validation

  • bash test/run.sh 3860_the_plan_graph_is_drawn_by_milestone

Evidence required

  • case_the_plan_graph_is_drawn_by_milestone

Evidence

None recorded. Every token above needs a command or an artifact behind it before this issue can be completed; narrative is refused.

Timeline

started
—
verified
—
completed
—

Those three fields, the evidence above and the state of the dependencies are all the status is made of. There is no status field to disagree with them.

Canonical record: .ai/repo/project/issues/I3841.yaml. Read it back with majordomus plan show I3841.