ci-critical-path — The critical path from a change to its verdict, and from a merge to its verified deploy, runs under a minute warm
The change-to-verdict path runs p50 under 40 s and p95 under 60 s warm, and merge-to-verified-deploy p50 under 45 s and p95 under 60 s, measured on GitHub with warm, partial and cold reported apart, every skip of a gate explained by the repository's own impact model, and no required test removed, skipped or made advisory to reach the number.
PLÁNOVÁNO 0 of 11 issues done
- připraveno
- 9
- blokováno
- 2
- aktivní
- 0
- verify
- 0
- hotovo
- 0
- zrušeno
- 0
Problém
A pull request's required verdict takes hours, not seconds: the behavioural suite runs on four shards of 51-86 minutes each, every documentation or layer change runs all four, and one case alone has cost up to 3468 s on a loaded runner. The suite budget has been raised three times in a week to follow runner load, and on 2026-10-09 the slowest case went 18 s over its 3450 s budget and failed the verdict of a pull request it does not touch (#831, run 37926379104). The owner's mission of 2026-10-08 asks for the change-to-verdict and merge-to-verified-deploy paths under 60 s warm, measured on GitHub, with no enforcement weakened.
Výsledek
The change-to-verdict path runs p50 under 40 s and p95 under 60 s warm, and merge-to-verified-deploy p50 under 45 s and p95 under 60 s, measured on GitHub with warm, partial and cold reported apart, every skip of a gate explained by the repository's own impact model, and no required test removed, skipped or made advisory to reach the number.
Aktuální stav
No baseline of the two paths is recorded on GitHub. .ai/repo/ci/suite.yaml budgets the suite at 56000 case-seconds and the slowest case at 3450 s, each re-derived from runner load. scripts/ci-plan selects the whole suite for 22 of 28 path classes, and no case declares the paths it reads (the 2026-10-08 measurement: 0 of 409).
Cílový stav
A measured baseline of both paths is committed before any redesign; each change that shortens them names the measurement it moves; and the budget of a case is never raised to follow runner load again.
Rozsah
- .ai/repo/project
- .ai/repo/ci
- .github/workflows
- scripts/ci
- scripts/ci-plan
- test/run.sh
- test/cases
Mimo rozsah
- Removing, skipping or making advisory any required test to reach the number
- Redesigning anything before the baseline of both paths is measured on GitHub and committed
- Local timings as the measure; the number is GitHub's
Kritéria přijetí
- The baseline of change-to-verdict and merge-to-verified-deploy, warm, partial and cold, is committed with the runs it was measured from
- Both paths meet the outcome's percentiles over the runs named, and every gate a change skips names the impact rule that skipped it
- No required test was removed, skipped or made advisory, shown by the gate model's required set before and after
Validace
- bin/majordomus plan validate
- scripts/ci-plan --check
Požadované důkazy
- baseline_measured_on_github
- critical_path_under_a_minute
Úkoly
Každý z nich je prováděcí kontrakt s vlastními kritérii přijetí, validačním příkazem a požadovanými důkazy. Sloupec wave je vrstva grafu závislostí, v níž úkol leží.
| issue | status | vlna | závisí na | název |
|---|---|---|---|---|
| I2115 | PŘIPRAVENO | 0 | — | The slowest case costs a fraction of its budget, and its budget is never raised to follow runner load again |
| I2348 | BLOKOVÁNO | 1 | I2350 | A gate's result is reused only for the exact inputs it judged, and a skipped gate carries the proof that nothing it reads changed |
| I2350 | PŘIPRAVENO | 0 | — | One gate model names what a local check, a pull request, an integration and a release must run, and no second inventory exists |
| I3824 | PŘIPRAVENO | 0 | — | The cooperation rule says a worker lands its own green head, and every bootstrap says the same |
| I3825 | BLOKOVÁNO | 1 | I3824 | A build refuses to start beside five others or below 35 GiB free |
| I3830 | PŘIPRAVENO | 0 | — | A local gate reports and CI decides: pre-commit and pre-push refuse only on integrity |
| I3831 | PŘIPRAVENO | 0 | — | A hook never starts a cold cargo build: a stale executable is the installed release, or the check is skipped and says so |
| I3832 | PŘIPRAVENO | 0 | — | majordomus worktree sweep removes merged, clean, idle worktrees, never with force, and announces each on the mesh |
| I3833 | PŘIPRAVENO | 0 | — | majordomus disk prune reclaims the container runtime's caches by name: build cache, anonymous unused volumes, dangling images, then trims the VM disk |
| I3834 | PŘIPRAVENO | 0 | — | A case run removes its own scratch dir however it ends: passed, failed, timed out or interrupted |
| I3839 | PŘIPRAVENO | 0 | — | A build that cannot take its build directory's lock never falls back to a cold private directory below the free-disk bound: it waits, bounded, or refuses naming the bound and the holder |
Graf
flowchart LR
I2115["I2115<br/>The slowest case costs a fraction of its budget, and its budget is never raised to follow runner load again"]:::ready
I2348["I2348<br/>A gate's result is reused only for the exact inputs it judged, and a skipped gate carries the proof that nothing it reads changed"]:::blocked
I2350["I2350<br/>One gate model names what a local check, a pull request, an integration and a release must run, and no second inventory exists"]:::ready
I3824["I3824<br/>The cooperation rule says a worker lands its own green head, and every bootstrap says the same"]:::ready
I3825["I3825<br/>A build refuses to start beside five others or below 35 GiB free"]:::blocked
I3830["I3830<br/>A local gate reports and CI decides: pre-commit and pre-push refuse only on integrity"]:::ready
I3831["I3831<br/>A hook never starts a cold cargo build: a stale executable is the installed release, or the check is skipped and says so"]:::ready
I3832["I3832<br/>majordomus worktree sweep removes merged, clean, idle worktrees, never with force, and announces each on the mesh"]:::ready
I3833["I3833<br/>majordomus disk prune reclaims the container runtime's caches by name: build cache, anonymous unused volumes, dangling images, then trims the VM disk"]:::ready
I3834["I3834<br/>A case run removes its own scratch dir however it ends: passed, failed, timed out or interrupted"]:::ready
I3839["I3839<br/>A build that cannot take its build directory's lock never falls back to a cold private directory below the free-disk bound: it waits, bounded, or refuses naming the bound and the holder"]:::ready
I2350 --> I2348
I3824 --> I3825
classDef done stroke:#16a34a,fill:#dcfce7,color:#14532d,stroke-width:2px
classDef active stroke:#2563eb,fill:#eff6ff,color:#1e3a8a,stroke-width:2px
classDef verify stroke:#7c3aed,fill:#f5f3ff,color:#4c1d95,stroke-width:2px
classDef ready stroke:#0891b2,fill:#ecfeff,color:#164e63,stroke-width:2px
classDef planned stroke:#0891b2,fill:#ecfeff,color:#164e63,stroke-width:2px
classDef blocked stroke:#b45309,fill:#fffbeb,color:#78350f,stroke-width:2px
classDef cancelled stroke:#6b7280,fill:#f9fafb,color:#374151,stroke-width:2px
classDef superseded stroke:#6b7280,fill:#f9fafb,color:#374151,stroke-width:2pxOdkazuje z tohoto diagramu (11)
- I2115 The slowest case costs a fraction of its budget, and its budget is never raised to follow runner load again
- I2348 A gate's result is reused only for the exact inputs it judged, and a skipped gate carries the proof that nothing it reads changed
- I2350 One gate model names what a local check, a pull request, an integration and a release must run, and no second inventory exists
- I3824 The cooperation rule says a worker lands its own green head, and every bootstrap says the same
- I3825 A build refuses to start beside five others or below 35 GiB free
- I3830 A local gate reports and CI decides: pre-commit and pre-push refuse only on integrity
- I3831 A hook never starts a cold cargo build: a stale executable is the installed release, or the check is skipped and says so
- I3832 majordomus worktree sweep removes merged, clean, idle worktrees, never with force, and announces each on the mesh
- I3833 majordomus disk prune reclaims the container runtime's caches by name: build cache, anonymous unused volumes, dangling images, then trims the VM disk
- I3834 A case run removes its own scratch dir however it ends: passed, failed, timed out or interrupted
- I3839 A build that cannot take its build directory's lock never falls back to a cold private directory below the free-disk bound: it waits, bounded, or refuses naming the bound and the holder
Canonical record: .ai/repo/project/milestones/ci-critical-path.yaml. Read it back with majordomus plan show ci-critical-path.